Construction schedule: Week of 7/13/2026

ፍሉጣት ንጥፈታት

  • Monday, July 13 – Friday, July 17: Early Morning Concrete Operations (12-4:00 AM Start)
    Concrete operations are scheduled for Monday through Friday of this week. The project’s first slab on-grade concrete placement will begin on Tuesday, July 14. Concrete pump setup will begin at approximately 12:00AM, with concrete pumping expected to begin around 1:00AM.  Concrete operations for the remainder of the week, including Monday, July 13, will continue on their typical schedule, with equipment arriving approximately at 4:00AM and concrete pours beginning around 5:00AM.

ኩሎም መሳርሒታት ኣብ ውሽጢ እቲ ኳዕቲ ኣብቲ ናይ ስራሕ ቦታ ክቐርቡ እዮም፣ ድምጺ ንምንካይ ዝሕግዝ ኣብ ዝከኣለሉ ቦታታት ናይ ድምጺ ኮቦርታታት ክተኽሉ እዮም። እቲ ናይ ፕሮጀክት ጉጅለ ኣብ ምሉእ እዞም ስርሒታት ደረጃ ድምጺ ምክትታል ክቕጽል እዩ፣ እዚ ድማ ጽልዋታት ንምንካይ ክሕግዝ እዩ። ናይ ኮንክሪት መካይን ብሰሜን ዝወስድ ጎደና ትሪኒቲ ኣቢለን ናብቲ ቦታ ክኣትዋ እየን።.

ቀጻሊ ስራሕ

  • ናይ ሰሙን ናይ ስራሕ ሰዓታት
    ንጥፈታት ኳዕትን ምጉዕዓዝን ካብ ሰዓት 7፡00 ቅድሚ ቀትሪ ክሳብ ሰዓት 10፡00 ድሕሪ ቀትሪ ክካየድ እዩ።.         
  • ናይ ሰሙን መወዳእታ ናይ ስራሕ ሰዓታት
    ንጥፈታት ኳዕትን ምጉዕዓዝን ካብ ሰዓት 8፡00 ቅድሚ ቀትሪ ክሳብ ሰዓት 7፡00 ድሕሪ ቀትሪ ክካየድ እዩ።. 

እዘን ሰዓታት ምስ ኣብ ከተማ ዝፍቀድ ይወድቃ ዝተናውሐ መስኮት ህንጸት።, ፣ ካብ ሰዓት 6፡00 ቅድሚ ቀትሪ ክሳብ ሰዓት 10፡30 ድሕሪ ቀትሪ ንጥፈታት ዝፈቅድ።. 

ጻዕርታት ድምጺን ምቅላልን።

ንጥፈታት ህንጸት ንጎረባብትና ዘይምቹእ ምዃኑ ኣስተውዒልና፡ ስጉምትታት ምቅላል ንምትግባርን ንምጽራይን ተወፋይነት ኣለና። እዋናውን ዝተሰፍሐን ጻዕርታት፤

  • ናይ ድምጺ ኮቦርታን ናይ ከባቢ መሳርሒታት መከላኸሊን ምጥቃም
  • ቀጻሊ ምክትታል ድምጺ፡ ምስ ደረት ከተማ ምትእስሳር ንምርግጋጽ ምክትታል ደሲቤል ሓዊሱ
  • ኣብ ዝከኣለሉ ናይ ምሸት ሰዓታት ዝለዓለ ጽልዋ ዘለዎም ንጥፈታት ምድራት
  • ስራሕ እናሰጎመ ምስ ከደ ተወሳኺ ናይ ምቅላል ስትራተጂታት ምግምጋም

ኣብ ዙርያ እቲ ዳግመ ልምዓት ዝግበረሉ ቦታ ትልሚ ትራፊክ

ኣብ እዋን ህንጸት፡ ውጥን ምቁጽጻር ትራፊክ፡ ኣብ ከባቢ ማእከል ዋዕላ ኣብ መንጎ ምብራቕን ምዕራብን ንዝጓዓዙ እግረኛታትን ተቐዳደምቲ ብሽክለታን ምብጻሕን ድሕነትን የረጋግጽ። ዝተነጸረ መስመር ናይ ጽዕነት መካይን ንናይ ጽዕነት መካይን ሓደ ኣንፈት ዘለዎ መንገዲ ዘለዎ ጽልዋ ትራፊክ ከጉድል እዩ።

Pedestrian Map

ኩነታት ህሉውን መጻእን ምዕጻው ጽርግያታት

ብቐጻሊ ዝመሓየሽ ካርታ ዞባታት ስራሕ ኣማንዳ ንኹሉ ምዕጻው ጎደናታትን ዕለታት ምዕጻውን ኣብ ከባቢ ኦስቲን ዘርኢ ኮይኑ፡ ምስ ዳግመ ምምዕባል ማእከል ዋዕላ ዝተኣሳሰር ምዕጻው ሓዊሱ።