Construction schedule: Week of 5/17/2026

NOTABLE ACTIVITIES

  • Tower Crane #2 Installation – Red River Partial Closure – Beginning May 31 at 10:00 PM
    Red River (between the Fairmont entrance and 3rd Street) will be closed beginning Sunday, May 31 at 10:00 PM and will remain closed through June 4 to support the installation of our second tower crane.  This will require overnight work on Sunday night, May 31 only, to set up the crane used to assemble the tower crane.  The tower crane assembly will happen during normal daytime hours from June 1 to June 4.

 

ONGOING WORK

  • Saturday–Sunday, May 16–17 – Weekend Work Hours
    Excavation and hauling activities are scheduled for Saturday and Sunday from 8:00 AM to 7:00 PM to help keep the project on schedule, reduce the overall duration of construction impacts, and support ongoing concrete operations.

    Monday–Friday, May 18–22 – Weekday Work Hours
    Excavation and hauling activities will run from 7:00 AM to 10:00 PM to help keep the project on schedule, reduce the overall duration of construction impacts, and support ongoing concrete operations.

    These hours fall within the City’s allowable extended construction window, which permits activity from 6:00 AM to 10:30 PM. Weekend work hours will remain unchanged, with operations limited to 8:00 AM to 7:00 PM.

Noise & Mitigation Efforts

We recognize the inconvenience of construction activity for our neighbors and remain committed to implementing and refining mitigation measures. Current and expanded efforts include:

  • Use of sound blankets and localized equipment shielding
  • Ongoing noise monitoring, including decibel tracking to ensure compliance with City thresholds
  • Limiting higher-impact activities during evening hours where feasible
  • Evaluating additional mitigation strategies as work progresses

재개발 부지 주변 교통 계획

공사 기간 동안 교통 통제 계획을 통해 컨벤션 센터 구역 동서 간 보행자와 자전거 이용자의 접근과 안전을 확보합니다. 트럭 통행로를 명확히 설정하여 트럭 일방통행으로 교통 체증을 최소화합니다.

Pedestrian Map

현재 및 향후 도로 폐쇄 현황

정기적으로 업데이트되는 AMANDA 작업 구역 지도는 오스틴 지역의 모든 도로 폐쇄 및 폐쇄 날짜를 보여 주며, 여기에는 컨벤션 센터 재개발과 관련된 폐쇄도 포함됩니다.