Construction Alerts

Construction schedule: Week of 7/13/2026

NOTABLE ACTIVITIES

  • Monday, July 13 – Friday, July 17: Early Morning Concrete Operations (12-4:00 AM Start)
    Concrete operations are scheduled for Monday through Friday of this week. The project’s first slab on-grade concrete placement will begin on Tuesday, July 14. Concrete pump setup will begin at approximately 12:00AM, with concrete pumping expected to begin around 1:00AM.  Concrete operations for the remainder of the week, including Monday, July 13, will continue on their typical schedule, with equipment arriving approximately at 4:00AM and concrete pours beginning around 5:00AM.

All equipment will be positioned within the excavation on the job site, with sound blankets installed where feasible to help minimize noise. The project team will continue monitoring sound levels throughout these operations to help reduce impacts. Concrete trucks will access the site via northbound Trinity Street.

ONGOING WORK

  • Weekday Work Hours
    Excavation and hauling activities will run from 7:00 AM to 10:00PM.         
  • Weekend Work Hours
    Excavation and hauling activities will run from 8:00 AM to 7:00PM. 

These hours fall with in the City’s allowable extended construction window, which permits activity from 6:00 AM to 10:30 PM. 

Noise & Mitigation Efforts

We recognize the inconvenience of construction activity for our neighbors and remain committed to implementing and refining mitigation measures. Current and expanded efforts include:

  • Use of sound blankets and localized equipment shielding
  • Ongoing noise monitoring, including decibel tracking to ensure compliance with City thresholds
  • Limiting higher-impact activities during evening hours where feasible
  • Evaluating additional mitigation strategies as work progresses

Traffic plan around the redevelopment site

During construction, a traffic control plan ensures access and safety for pedestrians and bicyclists traveling between east and west in the Convention Center area. A defined truck route will minimize traffic impact with a one-way path for trucks.

Pedestrian Map

Status of current and future road closures

Updated regularly, the AMANDA Work Zones Map shows all street closures and closure dates in the Austin area, including closures related to the Convention Center redevelopment.