Construction Alerts

Construction schedule: Week of 4/27/26

NOTABLE ACTIVITIES

Thursday, April 30 – Early Morning Concrete Pour (3:00 AM start)

Concrete placement for one of the building’s structural foundation elements will begin early Thursday morning. Concrete trucks will access the site via Trinity Street (northbound).

  • ONGOING WORK
    Excavation and hauling activities will run from 7:00 AM to 10:00 PM  to help keep the project on schedule, reduce the overall duration of construction impacts, and support ongoing concrete operations.

    These hours fall within the City’s allowable extended construction window, which permits activity from 6:00 AM to 10:30 PM. Weekend work hours will remain unchanged, with operations limited to 8:00 AM to 7:00 PM.

Noise & Mitigation Efforts

We recognize the inconvenience of construction activity for our neighbors and remain committed to implementing and refining mitigation measures. Current and expanded efforts include:

  • Use of sound blankets and localized equipment shielding
  • Ongoing noise monitoring, including decibel tracking to ensure compliance with City thresholds
  • Limiting higher-impact activities during evening hours where feasible
  • Evaluating additional mitigation strategies as work progresses

Plan de tráfico alrededor del sitio de reurbanización

Durante la construcción, un plan de control de tráfico garantiza el acceso y la seguridad de peatones y ciclistas que circulan entre el este y el oeste en la zona del Centro de Convenciones. Una ruta definida para camiones minimizará el impacto en el tráfico con un carril unidireccional para camiones.

Pedestrian Map

Estado de los cierres de carreteras actuales y futuros

Actualizado periódicamente, el Mapa de Zonas de Trabajo de AMANDA muestra todos los cierres de calles y las fechas de cierre en el área de Austin, incluidos los cierres relacionados con la reurbanización del Centro de Convenciones.