Construction Alerts

Construction schedule: Week of 11/15/2026

NOTABLE ACTIVITES

  • Tues., November 17 & Fri., November 20 – (12:00 AM Setup / 1:00 AM Concrete Placement)
    An elevated concrete deck pour is scheduled for early Wednesday morning. Concrete pump setup will begin at approximately 12:00 AM, with concrete placement expected to begin around 1:00 AM and continue for approximately 6 hours.

    Crews expect to continue cleaning and preparing walls for waterproofing, with shotcrete operations anticipated to resume in two to three weeks. Scheduled overnight concrete pours will continue as planned.

    All equipment will remain within the excavation, with sound blankets installed where feasible to help minimize noise. The project team will continue monitoring sound levels throughout these operations to help reduce impacts. Concrete trucks will access the site via northbound Trinity Street.

 

ONGOING WORK

  • Weekend Work Hours
    Work hours are anticipated to begin at 8:00 AM and extend until approximately 7:00 PM. No construction activities are currently planned for Sunday.

  • Extended Weekday Work Hours
    Construction activities are expected between 7:00 AM and approximately 8:00 PM on weekdays.

    These hours fall within the City’s allowable extended construction window, which permits weekday activity from 6:00 AM to 10:30 PM.

Noise & Mitigation Efforts

We recognize the inconvenience of construction activity for our neighbors and remain committed to implementing and refining mitigation measures. Current and expanded efforts include:

  • Use of sound blankets and localized equipment shielding
  • Ongoing noise monitoring, including decibel tracking to ensure compliance with City thresholds
  • Limiting higher-impact activities during evening hours where feasible
  • Evaluating additional mitigation strategies as work progresses

Traffic plan around the redevelopment site

During construction, a traffic control plan ensures access and safety for pedestrians and bicyclists traveling between east and west in the Convention Center area. A defined truck route will minimize traffic impact with a one-way path for trucks.

Pedestrian Map

Status of current and future road closures

Updated regularly, the AMANDA Work Zones Map shows all street closures and closure dates in the Austin area, including closures related to the Convention Center redevelopment.