重新構想未來的奧斯汀會議中心

10

多年醞釀

6

城市街區

1

轉型會議中心

Austin Art

支持公共藝術,金額為 $17.7M

時間軸

全速前進

2017 to 2021

Years of community engagement, in-depth studies, and a dedicated taskforce.

2019

Hotel Occupancy Tax Funding increase was approved.

Austin_Convention_Center_Redevelopment_and_Expansion_Analysis__2021

2023

City Council approved Design and Construction contracts.

 

April 2025

The previous Convention Center closed its doors but continues to hold events in other locations.

The existing Convention Center will officially close its doors.

 

2025 年 6 月

Excavation is underway and will continue through early 2026.

Excavation Commences

July 2025

City Council approved additional project authorizations.

 

September 2025

Structural demolition is 100% complete.

October 2025

Schematic design work complete.

Through 2028
Design work continues, along with continued community engagement.

2025 年 12 月

Diaphragm walls are going in, which will be reinforced concrete support for the new Convention Center.

Construction-Begins

開放時間:2029 年春季

為未來的奧斯汀做好準備!請回來查看我們未來空間的效果圖。

Open Spring 2029

2017 to 2021

Years of community engagement, in-depth studies, and a dedicated taskforce.

2019

Hotel Occupancy Tax Funding increase was approved.

Austin_Convention_Center_Redevelopment_and_Expansion_Analysis__2021

2023

City Council approved Design and Construction contracts.

 

April 2025

The previous Convention Center closed its doors but continues to hold events in other locations.

The existing Convention Center will officially close its doors.

 

2025 年 6 月

Excavation is underway and will continue through early 2026.

Excavation Commences

July 2025

City Council approved additional project authorizations.

 

September 2025

Structural demolition is 100% complete.

October 2025

Schematic design work complete.

Through 2028
Design work continues, along with continued community engagement.

2025 年 12 月

Diaphragm walls are going in, which will be reinforced concrete support for the new Convention Center.

Construction-Begins

開放時間:2029 年春季

為未來的奧斯汀做好準備!請回來查看我們未來空間的效果圖。

Open Spring 2029

2017-2021
副標題描述
Approved by the City Council, after years of community engagement, in-depth studies, and a dedicated taskforce.
2017-2021
2023
Subhead
City Council approved Design and Construction contracts.
2023
2025 年 4 月
結束語
The existing Convention Center closed its doors but continues to hold events in other locations.
2025 年 4 月
2025 年 6 月
挖掘工作開始
將為未來的會議中心騰出空間,以便再次開放街道網格。
2025 年 6 月
July 2025
Subhead
City Council approved additional project authorizations.
July 2025
2025 年 5 月
示範
將開始拆除現有建築物,為挖掘工作讓路。
2025 年 5 月
October 2025
示範
Schematic design work complete.
October 2025
2025 年 12 月
開始施工
建築從我們新創建的空間開始。
2025 年 12 月
2029 年 3 月考試
打開
為未來的奧斯汀做好準備!請回來查看我們未來空間的效果圖。
2029 年 3 月考試