Tái hiện Trung tâm Hội nghị Austin trong tương lai

10

Những năm trong quá trình thực hiện

6

Khối thành phố

1

Trung tâm hội nghị chuyển đổi

Austin Art

Hỗ trợ nghệ thuật công cộng, với số tiền $17.7M

Dòng thời gian

Tiến về phía trước với tốc độ tối đa

2017 to 2021

Years of community engagement, in-depth studies, and a dedicated taskforce.

2019

Hotel Occupancy Tax Funding increase was approved.

Austin_Convention_Center_Redevelopment_and_Expansion_Analysis__2021

2023

City Council approved Design and Construction contracts.

 

April 2025

The previous Convention Center closed its doors but continues to hold events in other locations.

The existing Convention Center will officially close its doors.

 

Tháng 6 năm 2025

Excavation is underway and will continue through early 2026.

Excavation Commences

July 2025

City Council approved additional project authorizations.

 

September 2025

Structural demolition is 100% complete.

October 2025

Schematic design work complete.

Through 2028
Design work continues, along with continued community engagement.

Tháng 12 năm 2025

Diaphragm walls are going in, which will be reinforced concrete support for the new Convention Center.

Construction-Begins

Mở cửa: Mùa xuân năm 2029

Hãy chuẩn bị cho tương lai của Austin! Hãy quay lại để xem bản vẽ không gian tương lai của chúng tôi.

Open Spring 2029

2017 to 2021

Years of community engagement, in-depth studies, and a dedicated taskforce.

2019

Hotel Occupancy Tax Funding increase was approved.

Austin_Convention_Center_Redevelopment_and_Expansion_Analysis__2021

2023

City Council approved Design and Construction contracts.

 

April 2025

The previous Convention Center closed its doors but continues to hold events in other locations.

The existing Convention Center will officially close its doors.

 

Tháng 6 năm 2025

Excavation is underway and will continue through early 2026.

Excavation Commences

July 2025

City Council approved additional project authorizations.

 

September 2025

Structural demolition is 100% complete.

October 2025

Schematic design work complete.

Through 2028
Design work continues, along with continued community engagement.

Tháng 12 năm 2025

Diaphragm walls are going in, which will be reinforced concrete support for the new Convention Center.

Construction-Begins

Mở cửa: Mùa xuân năm 2029

Hãy chuẩn bị cho tương lai của Austin! Hãy quay lại để xem bản vẽ không gian tương lai của chúng tôi.

Open Spring 2029

2017-2021
Mô tả tiêu đề phụ
Approved by the City Council, after years of community engagement, in-depth studies, and a dedicated taskforce.
2017-2021
2023
Subhead
City Council approved Design and Construction contracts.
2023
Tháng 4 năm 2025
Đóng cửa
The existing Convention Center closed its doors but continues to hold events in other locations.
Tháng 4 năm 2025
Tháng 6 năm 2025
Cuộc khai quật bắt đầu
Sẽ có không gian dành cho Trung tâm Hội nghị trong tương lai, cho phép mở rộng mạng lưới đường phố một lần nữa.
Tháng 6 năm 2025
July 2025
Subhead
City Council approved additional project authorizations.
July 2025
Tháng 5 năm 2025
Thử nghiệm
Sẽ bắt đầu phá dỡ tòa nhà hiện tại để mở đường cho việc khai quật.
Tháng 5 năm 2025
October 2025
Thử nghiệm
Schematic design work complete.
October 2025
Tháng 12 năm 2025
Bắt đầu xây dựng
Quá trình xây dựng bắt đầu trong không gian mới được chúng tôi tạo ra.
Tháng 12 năm 2025
Bài kiểm tra tháng 3 năm 2029
Mở
Hãy chuẩn bị cho tương lai của Austin! Hãy quay lại để xem bản vẽ không gian tương lai của chúng tôi.
Bài kiểm tra tháng 3 năm 2029