Spring 2029
오픈: 2029년 봄 오스틴의 미래를 준비하세요! 미래 공간의 렌더링을 다시 확인하세요.
2025년 12월
December 2025 Diaphragm walls are going in, which will be reinforced concrete support for the new Convention Center.
Oct 2025
October 2025 Schematic design work complete. Through 2028Design work continues, along with continued community engagement.
Sept 2025
September 2025 Structural demolition is 100% complete.
July 2025
July 2025 City Council approved additional project authorizations.
2025년 6월
June 2025 Excavation is underway and will continue through early 2026.
4월 2025
April 2025 The previous Convention Center closed its doors but continues to hold events in other locations.
2023
2023 City Council approved Design and Construction contracts.
2017-2021
2017 to 2021 Years of community engagement, in-depth studies, and a dedicated taskforce. 2019 Hotel Occupancy Tax Funding increase was approved.