미래의 오스틴 컨벤션 센터를 재구성하다

10

수년간의 제작

6

도시 블록

1

변형 컨벤션 센터

Austin Art

$17.7M의 곡조로 공공예술 지원

타임라인

전속력으로 전진하다

2017 to 2021

Years of community engagement, in-depth studies, and a dedicated taskforce.

2019

Hotel Occupancy Tax Funding increase was approved.

Austin_Convention_Center_Redevelopment_and_Expansion_Analysis__2021

2023

City Council approved Design and Construction contracts.

 

April 2025

The previous Convention Center closed its doors but continues to hold events in other locations.

The existing Convention Center will officially close its doors.

 

2025년 6월

Excavation is underway and will continue through early 2026.

Excavation Commences

July 2025

City Council approved additional project authorizations.

 

September 2025

Structural demolition is 100% complete.

October 2025

Schematic design work complete.

Through 2028
Design work continues, along with continued community engagement.

2025년 12월

Diaphragm walls are going in, which will be reinforced concrete support for the new Convention Center.

Construction-Begins

오픈: 2029년 봄

미래의 오스틴을 준비하세요! 미래 공간의 렌더링을 다시 확인하세요.

Open Spring 2029

2017 to 2021

Years of community engagement, in-depth studies, and a dedicated taskforce.

2019

Hotel Occupancy Tax Funding increase was approved.

Austin_Convention_Center_Redevelopment_and_Expansion_Analysis__2021

2023

City Council approved Design and Construction contracts.

 

April 2025

The previous Convention Center closed its doors but continues to hold events in other locations.

The existing Convention Center will officially close its doors.

 

2025년 6월

Excavation is underway and will continue through early 2026.

Excavation Commences

July 2025

City Council approved additional project authorizations.

 

September 2025

Structural demolition is 100% complete.

October 2025

Schematic design work complete.

Through 2028
Design work continues, along with continued community engagement.

2025년 12월

Diaphragm walls are going in, which will be reinforced concrete support for the new Convention Center.

Construction-Begins

오픈: 2029년 봄

미래의 오스틴을 준비하세요! 미래 공간의 렌더링을 다시 확인하세요.

Open Spring 2029

2017-2021
소제목 설명
Approved by the City Council, after years of community engagement, in-depth studies, and a dedicated taskforce.
2017-2021
2023
Subhead
City Council approved Design and Construction contracts.
2023
4월 2025
폐쇄
기존 컨벤션 센터는 문을 닫았지만 다른 장소에서 행사를 계속 개최하고 있습니다.
4월 2025
2025년 6월
발굴 시작
미래의 컨벤션 센터를 위한 공간이 마련되면 거리 격자가 다시 개방될 것입니다.
2025년 6월
July 2025
Subhead
City Council approved additional project authorizations.
July 2025
2025년 5월
데모
발굴 작업을 위해 기존 건물을 철거하기 시작합니다.
2025년 5월
October 2025
데모
Schematic design work complete.
October 2025
2025년 12월
건설이 시작됩니다
건물은 새로 만든 공간에서 시작됩니다.
2025년 12월
2029년 3월 시험
열려 있는
미래의 오스틴을 준비하세요! 미래 공간의 렌더링을 다시 확인하세요.
2029년 3월 시험