The Austin Convention Center redevelopment and expansion reached major milestones, and as of June 2026 is on track to open in early 2029. The Design Development Phase completed in October 2025, which means the project is now in its final design stage, which will continue through 2026.
Construction continues to move forward, with structural demolition and construction of the diaphragm wall—the first permanent structural element supporting the expanded six-block footprint—now complete. The first and second cranes have been installed, and the third and final crane is being installed. Crews have begun pouring the foundation, work which will continue throughout 2026.
Excavation is 65% complete, and as of June 2026, 746,000 cubic yards of soil have been removed with 154,000 cubic yards to go. This is equivalent to filling the Texas Capital Dome from floor to ceiling 13 times.
Check out the street level progress in the time-lapse videos below.
Sustainability is a top priority, and we’re on track to achieve an AEGB 4-star rating and LEED Gold certification. As part of the certification process, the work focused on salvaging, recycling, and repurposing materials from the original facility that would have gone to the landfill. This commitment started on day one, allowing us to exceed our 75% waste diversion goal by salvaging materials from the original structure—currently at a 79% diversion rate.
Some highlights:
These are just a few early steps toward meeting our ambitious sustainability goals—and we’re only getting started.
(current as of 6/30/2026)
Based on total dollars paid to date/total project cost
Based on total dollars paid to date/total excavation cost
Substantial Completion Q4 2028
88%
low carbon
180 ft
tall by 30 ft deep
Among the longest ever constructed
274
tons will be reused
All remaining steel has been recycled
90+
engagement events
For the latest developments, you can: