Spring 2029
ክፉት: ጽድያ 2029 ንመጻኢ ኦስቲን ተዳለዉ! ንናይ መጻኢ ቦታና ምቕራጽ ዳግማይ ርኣዩ።
ታሕሳስ 2025 ዓ.ም
December 2025 Diaphragm walls are going in, which will be reinforced concrete support for the new Convention Center.
Oct 2025
October 2025 Schematic design work complete. Through 2028Design work continues, along with continued community engagement.
Sept 2025
September 2025 Structural demolition is 100% complete.
July 2025
July 2025 City Council approved additional project authorizations.
ሰነ 2025 ዓ.ም
June 2025 Excavation is underway and will continue through early 2026.
ሚያዝያ 2025
April 2025 The previous Convention Center closed its doors but continues to hold events in other locations.
2023
2023 City Council approved Design and Construction contracts.
2017-2021
2017 to 2021 Years of community engagement, in-depth studies, and a dedicated taskforce. 2019 Hotel Occupancy Tax Funding increase was approved.