Spring 2029

خلاص: د ۲۰۲۹ کال پسرلی د راتلونکي آسټین لپاره چمتو اوسئ! زموږ د راتلونکي ځای د رینډرینګ لپاره بیرته وګورئ.

دسمبر ۲۰۲۵

December 2025 Diaphragm walls are going in, which will be reinforced concrete support for the new Convention Center.

Oct 2025

October 2025 Schematic design work complete. Through 2028Design work continues, along with continued community engagement.

Sept 2025

September 2025 Structural demolition is 100% complete.

July 2025

July 2025 City Council approved additional project authorizations.  

جون ۲۰۲۵

June 2025 Excavation is underway and will continue through early 2026.

اپریل ۲۰۲۵

April 2025 The previous Convention Center closed its doors but continues to hold events in other locations.  

2023

2023 City Council approved Design and Construction contracts.  

2017-2021

2017 to 2021 Years of community engagement, in-depth studies, and a dedicated taskforce. 2019 Hotel Occupancy Tax Funding increase was approved.